Update
They've just lifted 105 balcony in place. Very exciting to see.
Please be advised on the below outlook for this week;
General structure activities: Precast Install, General Formwork / Concreting / SteelfixingThere will be 2x major concrete pours next week - see below indicative dates (pending weather);Tuesday 10/10 (with contingency: 11/10)Thursday 12/10 (with contingency: 13-14/10)