161 EASTERN October 23rd Update

Update

General structure activities will be taking place for the remainder of the week through to next; Precast Install, General Formwork / Concreting / Steelfixing within normal working hours.

  • Pour 1 on Tuesday 24/10 (contingency 25/10)

  • Pour 2 on Friday 27/10 (contingency 28/10)